Dampier Barge Berth Facility

Client: Marine and Civil PTY LTD

Construction of a 60m quay face land-backed wharf (involving combiwall piling, tie-rod and anchor wall installation, structural steel framework, concrete works and associated wharf furniture), installation of 3no mooring dolphins, construction of rock armour sea walls and mass earthworks for a 10,000 m2 hardstand area.

  • 60m Quay Wharf Construction
  • Anchor pinning tubular piles: drilling and grouting
  • RORO ramp installation
  • 3no. Mooring Dolphins
  • Fabrication and installation of dolphin jackets
  • Diving operations
  • Earthworks
  • Import and placement of 90,000T bulk fill for land reclamation
  • Construction and removal of temporary piling bund
  • Construction of rock armour sea wall
  • Installation of scour protection¬†